Guidance for Davis-Bacon Compliance

State Revolving Fund (SRF) loan recipients are required to comply with the Davis-Bacon Act prevailing wage requirements. Federal Davis-Bacon Act requirements apply to construction contracts and subcontracts over $2,000. State Davis-Bacon requirements apply to contracts and subcontracts over $25,000.

Compliance with Davis-Bacon requirements requires a coordinated effort between the SRF Program, the loan recipient, the Construction Contractor, the Consulting Engineer, and the EPA. This guide is meant to help loan recipients keep track of Davis-Bacon requirements and milestones throughout the life of an SRF funded project.

Loan Agreement Preparation

Responsible party: SRF Program Staff
Action: Ensure that Davis-Bacon requirements are included in the loan agreement

Responsible party: SRF Program Staff
Action: Explain the Davis-Bacon clauses in the loan agreement to the Loan Recipient, as needed. Direct Recipient to website for SRF specification insert.

Advertisement and Bidding

Responsible party: Consulting Engineer
Action: Include the correct Davis-Bacon Wage Determination in the bid package. Private utilities must contact the SRF Program for wage determination approval by SRF Program Staff.

Responsible party: Consulting Engineer
Action: Ten (10) days before bid opening, check for an updated wage determination.

Responsible party: Consulting Engineer
Action: If an updated wage determination is published ten days prior to bid opening, the bid package must be updated by addendum to include the updated wage determination

Responsible party: Consulting Engineer
Action: If bid opening is postponed, recheck to see if an updated wage determination has been published. Include the updated determination if necessary

Responsible party: Consulting Engineer
Action:Include the SRF specification package in the project specifications

Award of Contract

Responsible party: Loan Recipient
Action: If the contract is not awarded within 90 days of the bid opening, update the wage determination in the awarded contract with the most current wage determination

Responsible party: Loan Recipient
Action: Provide a copy of the executed construction contract that includes the correct wage determination to the SRF Program.

Construction

Responsible party: Construction Contractor
Action: Pay all laborers and mechanics on the job the Davis-Bacon prevailing wage rate.

Responsible party: Construction Contractor
Action: Document the value of any fringe benefits if the fringe benefits represent part of the prevailing wage

Responsible party: Construction Contractor
Action: Submit weekly certified payrolls to the loan recipient. The certification statement on the payrolls must be signed

Responsible party: Construction Contractor
Action: Post the wage determination and Davis-Bacon information posters on the job site

Responsible party: Loan Recipient
Action: Spot check the certified payrolls against the wage determination. Review the Questions and Answers section for more guidance.

Responsible party: Loan Recipient
Action: Conduct wage rate interviews to ensure that the correct wages are being paid to the laborers and mechanics on the project. See Questions and Answers section for more guidance

Responsible party: Construction Contractor
Action: Responsible for ensuring that all subcontracts include the wage determination and required Davis-Bacon language, and that all subcontractors are aware of the Davis-Bacon requirements, pay weekly, and submit certified payrolls

Responsible party: Loan Recipient
Action: Ensure that Davis-Bacon requirements are being met. Each disbursement request to the SRF Program includes a statement certified by the loan recipient acknowledging compliance with Davis-Bacon requirements.

Responsible party: SRF Program Staff
Action: Verify that the fund recipient is doing their part and that systems are in place for verifying payrolls and conducting interviews

Project Closeout

Responsible party: SRF Program Staff
Action: Collect and check Davis-Bacon wage interviews

Responsible parties: SRF Program / EPA
Action: The SRF Program may request to inspect project records as part of a project inspection. In addition, EPA audits several of the SRF Program loans every year. For loans that EPA audits, the EPA may request certified payrolls and documentation of interviews. EPA will review the wage determination included in the executed contract.

Questions and Answers

If you have not yet awarded the contract, you can include the required language in the bid package through an addendum.

If, for example, you advertised your project before securing SRF funding, you can add the required language to the contract by change order. Prevailing wages must be paid to laborers and 
mechanics for the entire project. This may require the construction contractor to adjust payroll going back to the start of the project

Davis-Bacon wages only apply to laborers and mechanics employed by the construction contractor or subcontractors. Public utility staff and engineering consultants are not covered by Davis-Bacon Act prevailing wage requirements.

No, prevailing wages must be paid to laborers and mechanics for the entire project. A “project” is considered to be all the work performed under a contract for construction. If you are managing 
multiple construction contracts and multiple funding sources, be very careful to ensure that the correct funding requirements are applied to the correct contracts.

There are four types of wage determinations: Heavy, Highway, Residential, and Building. Drinking water, wastewater and stormwater construction is generally “Heavy.” If the project includes 
significant amounts of pavement, or an enclosed building, the “Highway” or “Building” schedules may be necessary.

Loan Recipients conduct interviews in order to ensure that their construction contractor is complying with the Davis-Bacon Act prevailing wage requirements. The interview should use 
Standard Form 1445 which includes all the required questions. You can get SF-1445 from the US General Services Administration. The loan recipient should establish an interview schedule to ensure that the contractor is complying. SRF staff can work with you to determine an interview schedule that provides reasonable assurance that you are exercising due diligence. At a minimum, one interview must be conducted per construction project. EPA suggests that interviewing 10% of the employed laborers and mechanics is a good guideline for larger projects.